Timeline of the High School/Middle School Project

2005:

Aug - JM School Board approves Master Plan

Nov - Ohio School Facilities Commission gives approval of Expedited Local Partnership Program agreement

2006:

Nov - Start Project; Prepare Program of Requirements

Dec - Construction Manager confirms budget

2007:

Feb - JM School Board/OSFC Approve POR

Mar - Prepare Schematic Design

Apr - Geotechnical Soil Investigation

June - JM School Board approves Schematic Design

Aug - Groundbreaking Ceremony

Summer 2007: Design Development Phase

Fall 2007: Sitework Begins

Winter 2007: Construction Document Phase

Spring 2008: Building Construction Begins

Fall 2009: Building Occupancy

Timeline of the Public Library Project

2007: Plan Development and Concept

* * * * * * * * * * * * * * * * * * * 

Bus Parking Project

This area will become the district's first centralized bus parking area. For years, drivers have taken their buses home and parked them on their own property, a practice frowned upon by law enforcement and insurance personnel. Homeland Security and a recent Ohio Law now recommend that all public school buses be parked in secured, locked areas.

Phase one of this project will be for bus parking and fueling only. The area is now surrounded by an eight foot fencing with overhead lights. A new fuel tank will soon be installed.

Phase two of this project contains plans for a maintenance/bus repair building and blacktop paving over the entire surface.

In preparation for the sitework to begin on the new JM High School/Middle School campus, you will notice the trailer of our construction management firm, The Ruhlin Co., is on this site. During this construction period, this trailer will also be available to our transportation department.